“Court Orders Halt To Construction” — Excavator Leaves UNILORIN Campus After Students’ Protest Over Disputed Land

An excavator used for construction work on a disputed portion of land at the University of Ilorin (UNILORIN), Kwara State, has been seen leaving the institution’s main campus, days after students protested against the project and a court issued an interim injunction restraining further construction activities at the site.

The development comes amid concerns over the excavation of a section of road between the university’s College of Health Sciences and Faculty of Pharmacy, which students said was disrupting movement and could affect access to lectures.

A video obtained by PREMIUM TIMES on Sunday, November 15, 2026, showed the excavator being moved out of the university premises.

However, the circumstances surrounding the removal of the equipment remain unclear, as it has not been established whether the development followed the court’s order, a decision by the contractor or an arrangement with the university management.

The excavator’s departure comes four days after students, led by the Students’ Union President, Adam Mozeed, staged a protest on November 11 over the ongoing excavation work.

During the protest, the students expressed concern that the construction activities were affecting movement within the campus, particularly for students of the College of Health Sciences and the Faculty of Pharmacy.

They also questioned the decision to commence work on the affected road without adequate consultation or an explanation of the project’s scope and duration.

Speaking during the protest, Mozeed accused the university management of failing to adequately engage students and other stakeholders before the commencement of the construction work.

“We don’t know how long it’s even going to take. There was no problem with stakeholders’ engagement,” he said.

The Students’ Union President called on the university authorities to explain the reasons for excavating the road, the expected duration of the project and the measures being taken to minimise disruption to students’ academic activities.

Meanwhile, the students’ protest coincided with an interim injunction obtained by the university against Craneburg Construction Company Limited and other persons whose identities were unknown.

In an order dated November 11, 2026, the Upper Area Court 1, Ilorin, restrained the construction company, its agents, privies and anyone acting through them from further clearing, constructing, developing or trespassing on the disputed land between the university’s College of Health Sciences and Faculty of Pharmacy.

The order followed an ex parte application filed by the university in Suit No. UACI/CVF/1173/2026.

After considering the application, the court granted the interim injunction, directing that the restriction remain in force pending the hearing and determination of the university’s motion on notice.

The order, signed by Judge S. H. Ajumobi, also adjourned the matter until November 16, 2026, for the hearing of the motion.

The injunction temporarily restrains further construction and development activities on the disputed land but does not constitute a final determination of ownership or the substantive rights of the parties.

Although the excavator has now been seen leaving the university premises, it remains uncertain whether the contractor has permanently withdrawn from the project or whether other construction activities have ceased.

The video showing the removal of the equipment does not establish the reason for its departure or whether it was moved in compliance with the court’s interim order.

The university management has yet to publicly explain the circumstances surrounding the construction work, address the concerns raised by the protesting students or clarify the implications of the court’s decision.

It is also unclear whether the institution and the contractor have reached any agreement concerning the disputed land or the removal of construction equipment.

The matter is expected to return before the Upper Area Court 1, Ilorin, on Monday, November 16, 2026, when the university’s motion on notice is scheduled for hearing.